K5F Gas Field

K5F Gas Field, Netherlands

The K5F field is located in block K5 in the Dutch sector of the North Sea, approximately 110km northwest of Den Helder. It is operated by Total E&P Nederland BV of behalf of its partners Energie Beheer Nederland BV, Goal Petroleum (Netherlands) B, Dyas BV and Lundin Netherlands BV.

"The K5F field is located in block K5 in the Dutch sector of the North Sea, northwest of Den Helder."

The field is planned to come on-stream in late 2007, where it should eventually reach a plateau of around 2.6 million cubic metres of gas a day. The total budget for the project has been estimated at more than €170m.

K5F SUBSEA INSTALLATIONS

The basis of the K5F field development is that it will be produced by means of two subsea production installations.

The jack-up drilling rig Ensco 72, which will be used to drill these wells, will also be used to install the two Christmas trees.

The produced gas will be then exported through a new 10km-long, 8in-diameter subsea pipeline. This will be connected to the existing K6N satellite platform. The gas treatment facility on the K6N satellite platform will be modified in order to process the K5F gas. From there flow will be exported via the K6 central complex for delivery to shore under contract to Gasunie for supply to the local gas network.

Subsea 7 received a contract valued in excess of $70m for engineering, procurement, construction and installation of the 8in-diameter flowline and umbilical systems, together with the associated tie-in and pull-in operations. The contract also included the engineering, procurement, fabrication and installation of the subsea protective structure complete with the pipeline end manifold, integrated umbilical distribution equipment and associated activities.

The massive 160t subsea cover was subcontracted to engineering contractor, Isleburn where it was built at the company's Nigg facility in a contract worth £800,000. The subsea cover was loaded onto a barge by a 500t crane at Isleburn's Nigg facility, for subsequent transfer to DSV Toisa Polaris. It was transported 400 miles to the K5F field in 48 hours.

ALL-ELECTRIC CHRISTMAS TREE

The keynote of the K5F project is that it will mark the first worldwide implementation of an all-electrical Christmas tree as opposed to the more common arrangement where the downhole valves are operated hydraulically. Cameron was awarded the contract by Total E&P for the supply of this all-electric subsea production system.

"The K5F field development is that it will be produced by means of two subsea production installations."

This unique system, powered by direct current, is designed to dramatically improve reliability, availability and maintainability. The system has no batteries or accumulators and much of the conventional electro-hydraulic equipment has been simplified or eliminated.

The operation and control and operation of the subsea installation will be from the K6 central complex, around 17km away. In addition, the surface platform will contain tanks and pumps for the mono ethylene glycol to prohibit the formation of hydrates in the pipeline.

Deployment is planned for mid-2007 with production to start in late in the year. The control system is configured for expansion to four wells.

By eliminating hydraulics for power and signals, the control-system commands can be sent in rapid succession, thus avoiding the lag time required for accumulator charging. High-speed communication provides near-instantaneous communication with equipment as well as feedback on subsea conditions.

The all-electric system eliminates the potential for hydraulic leaks and the issue of hydraulic-fluid disposal. This system includes an electric subsea control module, a power-regulation and communications module, electrically actuated chemical-injection valves, annulus and production gate valves, and an electrically actuated choke.

Long-term plans for K5F are said to include as many as four wells on the development, three on one template and a further step-out. The decision on this will be taken in 2008.

Printable Version Click here for printable version



Expand Image
Map of the K5 block.
Map of the K5 block.
Expand Image
The massive 160t subsea cover was subcontracted to engineering contractor, Isleburn.
The massive 160t subsea cover was subcontracted to engineering contractor, Isleburn.
Expand Image
The DSV Toisa Polaris which transported the subsea cover 400 miles to the K5F field.
The DSV Toisa Polaris which transported the subsea cover 400 miles to the K5F field.
Expand Image
The K5F project will be first worldwide implementation of an all-electrical Christmas tree.
The K5F project will be first worldwide implementation of an all-electrical Christmas tree.
Expand Image
Cameron was awarded the contract by Total E&P for the supply of the all-electric subsea production system.
Cameron was awarded the contract by Total E&P for the supply of the all-electric subsea production system.
Expand Image
The all-electric system eliminates the potential for hydraulic leaks and the issue of hydraulic-fluid disposal.
The all-electric system eliminates the potential for hydraulic leaks and the issue of hydraulic-fluid disposal.


client logon
Home
New On This Site
Products & Services
Company A-Z
Special Features
White Papers
Jobs & Careers
Industry News
Advertise With Us
Events & Exhibitions
Newsletter
About Us
Atom FeedRSS Feed
What is RSS?