| EXPORT | |
| Off-take tankers will be moored in tandem for crude oil transfer via an off-take loading hose. | |
| licence AC/P8 | Re-issued 1991 |
| WA/260-P | issued 1995 |
| AC/LC | issued 1997 |
| water Depth | 325 m - 420 m |
| distance to Darwin | 550 km |
| ENVIRONMENTAL | |
| reinjection of excess Gas | |
| prepared for low - Nox | |
| burners on Turbines | |
| produced water treatment (hydrocyclones) | |
| design Capacities | |
| oil Production | 27,000 Sm3/sd |
| gross Capacity | 38,000 Sm3/sd |
| gas Re-injection (gas / LPO) | 1.2 MMSm3/sd |
| gas Lift | 1.7 MMSm3/sd |
| number of wells (at Start-Up) | |
| oil producer (L) | 3 |
| oil producer (C) | 2 |
| gas Injectors | 1 |
| reservoir Data | |
| Laminaria/plover | |
| depth to oil / water Contact | 3,288 mss |
| oil Column | 103 m (Lam-1) |
| gas / oil Ratio | 42 Sm3 / Sm3 |
| fpso Data | |
| Storage | 1.4 million bbl |
| length Overall | 273 m |
| width Overall | 50 m |
| height to upper Deck | 28 m |
| Draught | 18.7 m |
| Displacement | 222,000 tonnes |
| Lt. unit weight (phase I) | 30,300 tonnes |
| Lt. unit weight (phase II) | 43,500 tonnes |
| exploration and appraisal Wells | |
| Laminaria-1 | drilled in oct 1994 (discovery well) |
| Laminaria-2 | drilled in may 1995 |
| Laminaria-3 and | drilled in Oct-dec 1995 |
| Laminaria-3 s/track | (appraisal wells) |
| Corallina-1 | drilled in dec 1995 |
| Investments | phase i (including drilling) A$ 1.3 billion |
| drainage Strategy | natural water Influx |
| gas lifted Production | |
| gas Injection | |
| number of risers (at Start-Up) | |
| production (2L, 1C) | 3 |
| gas Injection | 1 |
| gas lift etc | 2 |
| Electro-hydraulic Umbilical | 1 |
| accommodation (FPSO) | |
| maximum Capacity | 94 persons |
| normal manning during Operations | 37 persons |
| Featured Suppliers |
| ABLE Instruments & Controls - Oil and Gas Measurement / Control Solutions |
| Aker Kvaerner Eureka Pump Systems - Offshore Platforms, FPSOs and Subsea Installations |
| Aker Kvaerner Process Systems - Process Systems and Complete Process Trains for the Oil and Gas Industry |
| Champion Environmental Technologies - Anti-Fouling Products |
| Dillinger Hütte GTS - Steel Heavy Plate |
| IMECA - Hydraulic and Electric Traction and Storage Winches, A-Frames, Flexible Pipe Laying Systems, Chain Tensioners, Electric and Automation Engineering |
| Ingersoll-Rand - Air-Operated Hoists and Winches, Air Motors |
| K. LUND Offshore AS - Offshore Compressors for Plant and Instrument Air, Reciprocating Air and Gas Compressors, Nitrogen Boosters and Air Dryers |
| Karmsund Maritime Offshore Supply - Development, Production, Supply and Sale of Patented Offshore Tools and Equipment |
| Kongsberg Maritime, Process Simulation Unit - Dynamic Simulation Studies, Process Simulators and Production Management Systems |
| LEWA - Metering Pumps, Process Diaphragm Pumps and Engineered Pumping Solutions |
| Mareco - Chemical Injection Valves for Subsea Oil and Gas Production Systems |
| MCT Brattberg - Seal Blocks for Cables and Pipes |
| MEDC - Explosion Proof Alarm, Signal, Control and Communications Equipment |
| ORGA - Aids to Navigation and Helideck Lighting Packages |
| Proclad International - Pipe Cladding, Clad Pipes and Unclad Pipeline Components |
| Sandvik Powdermet - Efficient Boilers for the Production of Green Power |
| Semco Maritime - Design, Fabrication and Servicing of Turnkey Offshore Equipment |
| Solent Composite Systems - ProTek™ Composite Passive Fire and Blast Restraint Systems |
| Stromme Betex - Customized Offshore Filtration |
| Umoe Schat-Harding - Freefall Lifeboats, Rescue Boats and Survival Crafts |
| Voith Turbo - Variable Speed Power Transmissions and Variable Speed Drives |