Wonnich,

Specifications - Wonnich, Carnarvon Basin, Australia


Locationcarnarvon Basin, Australia
OperatorApache
first deliveryoctober 1999
Licencelicence TL/8
distance from onshore25 kilometres north west of varanus Island.
Discoveryjuly 1995
follow up wellsWonnich-2 august 1997
wonnich 3 october 1997
project go-ahead1998
Partners
Apache68.5%
tap oil NL12.2229%
kufpec Australia19.2771%
Reserves214 petajoules of gas at the 50% probability level
4.1 million barrels of condensate in place.
Platformthree-leg lattice platform
water depth30 metres
height above sea level25 metres
topsides weight115 tonnes
total jacket weight335 tonnes
main piles and insert piles195 tonnes
total weight645 tonnes
design throughput120 terajoules per day (tj/d)
the main deck16 metres by 6.3 metres
Wellsone producing well and three spare slots
platform equipmentboat access and helideck
platform crane
chemical injection
automation for remote control
solar and TEG.dc power system
Fabricationfebruary 1999
load outMarch
Installationensco 56 jack-up drill rig
Exporttwo 8in diameter pipelines
Pipeline31 km
amongst the main contracts were;
BARBOSplatform design, supply and installation
brown & Rootengineering and project management
asc Engineeringequipment packages for varanus Island
brown & Root-AOCinstallation works on varanus Island
Marubenisupply and coating of pipeline material
clough Offshoreoffshore pipeline installations.
Featured Suppliers
Semco Maritime - Design, Fabrication and Servicing of Turnkey Offshore Equipment


client logon
Home
New On This Site
Products & Services
Company A-Z
Special Features
White Papers
Jobs & Careers
Industry News
Advertise With Us
Events & Exhibitions
Newsletter
About Us
Atom FeedRSS Feed
What is RSS?