Floating production storage and offloading (FPSO) vessels operator BW Offshore, through its affiliate BW Energy, has revised development plan for Ruche project, including the Hibiscus discovery, located in the Dussafu Marine license offshore Gabon.

The revised plan will result in higher production from Ruche phase one development, which is estimated to double from 15,000bpd to 30,000bpd. Changes to the Ruche project follow the recent successful Hibiscus exploration well (DHIBM-1).

The contemplated Ruche platform will be moved approximately 4km to the west of the current position to incorporate the Hibiscus resources. Ruche phase one development will comprise four Hibiscus production wells and two Ruche wells, all from the Gamba formation in South Gabon.

BW Energy CEO Carl Arnet said: “Hibiscus is proving to be a discovery of equal quality and magnitude to the Tortue field.

“The revised development will add significantly to our production capacity and take us above the FPSOs current nameplate of 40,000bpd/day.”

The estimated capex for the revised Ruche phase one has been increased to $445m from the original capex which was estimated at $375m.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

BW Energy noted that it has agreed options for additional two exploration wells with the drilling contractor Borr Drilling, extending the current drilling campaign to the third quarter of 2020, provided the options are exercised.

Arnet added: “We are considering using one or two of these options based on our successes to date and the number of prospects we have identified.

“We also expect results from ongoing seismic reprocessing by year-end which combined with information from the ongoing drilling campaign will provide valuable data points.”

The company plans to fund the Ruche phase one development from its existing liquidity and cash-flow from operations.