United Completes Longest-Ever Continuous Tite Liner® Installation

Tite liner installation

Pipeline rehabilitation specialist United Special Technical Services (USTS), a joint venture between United Pipeline Systems and STS, has completed the longest-ever continuous compression-fit liner insertion project in its history. The project, undertaken using United Pipeline Systems’ Tite Liner® technology, lined an 8,200ft section of offshore produced water disposal pipeline.

There were a variety of challenges associated with the project in addition to the record-breaking length. First was the jobsite footprint. Limited space on the island necessitated that all the works related to the host pipeline as well as the HDPE liner were to be carried out offshore. Additionally, the project timing was not favorable. The only available weather window was during the summer, where the HDPE pipe surface was measured midday at 80°C. Therefore, any attempted pull would have to be performed at night in order to avoid extreme heat.

In addition, fusion joint welding of the HDPE pipeline was performed on a work barge tied to the pipelay vessel. Each 50-ft length of HDPE pipe was assembled into larger 150ft sections on the work barge. A watertight towing head was then fused to the lead 45m length and attached to the winch located on a tug. The tug would tow and guide the string of pipe, along with buoys to keep the pipe afloat, with the assistance of the work boats. The sea conditions required that the control of the pipe had to be decisive, as any over pulling by the tug would result in damaging the HDPE. Owing to the combined expertise of VMGL, USTS fusion and marine crews, the fusion operation was performed successfully.

One other issue was location. As a result of the steel pipe location, it was necessary to assemble the equipment inside the welding tunnel of the pipelay vessel. Additional structures and reinforcement supports were added and the tunnel roof was modified so that it could be removed. This enabled the equipment to be positioned and safely restrained to prevent any movement during the insertion.

Following the fusion jointing and testing, the HDPE pipe was positioned on the pipelay vessel with the pipe entry point at roughly 20ft above the sea surface. A special entry chute was actually constructed to ensure that the joints of the pipe were not overstressed during the pull.

At the time of installation, the winch pack was positioned on Halul Island and radio communication established. The preparation for the insertion started at 8pm. Once preparation was complete, the liner insertion commenced at approximately 2am and the entirety of the liner was installed by 6am.

USTS general manager Jeff Schell said: "Despite challenging conditions, with the combination of experience and our Tite Liner® technology, this project proved lining long distance pipelines can be accomplished offshore with solid wall interactive PE liners."

The produced water disposal pipeline now has internal corrosion protection from end to end to ensure it remains operational for its entire service life.

Schell added: "Every detail had to be attended to in this critical offshore environment where there is no margin for error. We faced many challenges but in the end we were successful."

The concrete weight coating (CWC) is a plant-applied coating used to provide negative buoyancy for offshore pipelines or for river or road crossing applications.
Aegion is globally positioned in the business of pipe protection and infrastructure life extension with corrosion control engineering and cathodic protection by Corrpro Companies.
A pipe collapse can have catastrophic effects on plant operations, your budget and your bottom line. Insituform can help you avoid the costs of a...
NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Friday. The industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU

Thank you for subscribing to Offshore Technology