Daandine is a producing cbm field located onshore Australia and is operated by Arrow Daandine . The field is located in block PL 230.

An expansion project is associated with the Daandine, namely Surat Gas Project – Daandine Phase 1. This project is currently in the construction stage, expected to start in 2022.

Field participation details

The field is owned by Shell and China National Petroleum.


Production from Daandine

The Daandine cbm field recovered 10.38% of its total recoverable reserves, with peak production expected in 2028. The peak production will approximately 670 Mmcfd of natural gas. Based on economic assumptions, production will continue until the field reaches its economic limit in 2045. The field currently accounts for approximately 1% of the country’s daily output.


Remaining recoverable reserves

The field is expected to recover 371.59 Mmboe, comprised of 2,229.55 bcf of natural gas reserves. Daandine cbm field reserves accounts 8.75% of total remaining reserves of producing cbm fields globally.


Contractors involved in the Daandine cbm field

Some of the key contractors involved in the Daandine project as follows.

Design/FEED Engineering: Worley

EPC Contractors: Valmec

Methodology

Information on the field is sourced from GlobalData’s fields database that provides detailed information on all producing, announced and planned oil and gas fields globally. Not all companies mentioned in the article may be currently existing due to their merger or acquisition or business closure.