The 462km-long, upcoming Dos Aguilas Project will be operated by Dos Aguilas. This onshore, product pipeline, with a maximum diameter of 20 inches, will start in Texas (the US) and ends in Monterrey (Mexico).
The Dos Aguilas Project is expected to commence operations in 2024 and will be owned by YPF, Empresa Nacional del Petroleo, and Chevron.
During the period 2021-2025, the Dos Aguilas Project is expected to witness an estimated capex of $372m.
Methodology
Information on the pipeline is sourced from GlobalData’s Oil & Gas Pipelines database that provides detailed information on all active and upcoming, crude oil, natural gas, petroleum products and Natural Gas Liquids (NGL) trunk pipelines globally. Not all companies mentioned in the article may be currently existing due to their merger or acquisition or business closure.