The Canada Energy Regulator (CER) has approved the request for route deviation of the multi-billion-dollar Trans Mountain oil pipeline expansion project.

The CER’s decision comes after a three-day hearing held in Calgary last week.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

The expansion project is essentially a twinning of the original Trans Mountain Pipeline, which was built in 1953 and remains operational to this day.

Last month, state-backed Trans Mountain Corp (TMC), which is building the new pipeline, applied to alter the route for a 1.3km section of the pipeline in Kamloops, British Columbia.

TMC said that the new path avoids micro-tunnelling construction, which is not viable technically and economically.

It added that if micro-tunnelling is required, the pipeline segment in question might not be finished until December 2024, according to Reuters.

Originally, the pipeline was expected to commence operations in January 2024.

The company proposed to install the pipeline via a different route close by using horizontal directional drilling and a traditional open trench technique.

However, the plan was opposed by the Stk’emlupsemc te Secwepemc Nation (SSN) First Nation, an indigenous group.

According to SSN, the area where the pipeline would pass “holds profound spiritual and cultural significance to the nation and peoples”.

The regulator did not provide a reason for its decision, which is expected to be released in the coming weeks.

The new 1,150km pipeline between Strathcona County, Alberta, and Burnaby, British Columbia, will carry an additional 590,000 barrels of oil sands petroleum to Canada’s Pacific Coast daily.

Once fully operational, the pipeline is expected to enhance Canada’s capacity to export crude oil to the west coast of the US and Asia.

The project, which has been plagued by years of delays, is expected to cost C$30.9bn ($22.97bn), over four times its initial budget.

Last month, media reports emerged that the Canadian Government could sell its stake in the Trans Mountain oil pipeline to indigenous groups.