Babbage gas field is located in Block 48/2 of the North Sea.
The topside of the Babbage gas field under construction.
The Babbage platform, a normally unmanned installation, is used to produce the field.
Babbage is produced through five horizontal production wells.
Pipe laying work in the sea at the Babbage gas field.
The towed platform being shipped for installation at the offshore site.

Babbage was found by the 48/2-2 discovery well in 1988

Babbage gas field is located in Block 48/2, about 80km offshore of the UK in the North Sea. It lies in 139ft (42m) of water and is the largest gas accumulation in the southern North Sea.

E.ON Ruhrgas is the operator of the field, with 47% interest. Partners include Dana Petroleum (40%) and Centrica Resource (13%).

The field has been developed in two phases with an investment of €350m ($440m). The first phase of development commenced production in August 2010. Phase two development was completed in May 2011. Life of the field is estimated to be 20 years.

Discovery of well 48/2-2 and 48/2a-4

Babbage was found by the 48/2-2 discovery well in 1988. It was deemed uneconomical, as the discovery well flowed at the rate of only 3.8 million standard cubic feet each day (mmscfgd).

An appraisal well, 48/2a-4, was drilled in July 2006 to a depth of 11,000ft. The well targeted the crestal area of the reservoir and flowed at a rate of 11mmscfgd. It established the presence of significant gas reserves.

Geology and reserves of Block 48/2 in the North Sea

The Babbage field’s reservoir lies at a depth of 3,200m in the lower Leman Sandstone formation. It is a north-west trending tilted fault block, which created tightly fault-sealed compartments. The reservoir comprises of an 80ft thick upper interval and a 200ft thick lower interval.

Estimated reserves of the field are five billion cubic metres of gas. The field contains good quality gas with low inert gas percentages and 93% methane.

Development details for the Babbage gas field

Babbage field development was approved in 2009 by the UK Government. The field is produced through five horizontal production wells. Three wells, B1, B2z and B3, were drilled during the first phase of development, followed by another two during the second phase.

“Babbage field development was approved in 2009 by the UK Government. The field is produced through five horizontal production wells.”

The reservoir includes five main production targets, with the C layer being the main target. Development of the field presented many challenges due to the structure of the reservoir.

Schlumberger’s Petrel modelling software was used to create a visualisation and optimise the well planning and placement process. Each well includes long horizontal drains to ensure maximum gas recovery. Hydraulic fractures spaced 800ft apart were used to penetrate the tightly fault-sealed compartments of the field reservoir.

Phase one wells were drilled using a wired drill pipe and motorised rotary-steerable system. The first well, B1, encountered several sub-seismic faults and required inclination corrections. Drilling of the B1 well helped in refining the drilling process of the B2z and B3 wells. The technology used to drill the B1 well ensured that the B2z and B3 wells met their targets.

The five production wells are connected to the Babbage platform. The platform is a normally unmanned installation installed in 42m of water. It was constructed in a period of ten months, employing nearly 500 people.

Exporting gas produced at E.ON Ruhrgas’ field

The gas produced from Babbage is transported through a 28km long, 12in diameter carbon steel pipeline to the West Sole Bravo platform. From West Sole, the gas is exported to the Dimlington gas terminal in Easington, east England.

Contracts awarded for the North Sea field’s development

Ode won the contract to conduct the conceptual engineering and FEED studies for the topside facilities of the Babbage platform.

“E.ON Ruhrgas is the operator of the field, with 47% interest. Partners include Dana Petroleum (40%) and Centrica Resource (13%).”

SLP Engineering was responsible for the construction of the platform. It subcontracted Merpro to supply three proppant removal packages.

Technip was awarded a €32m ($40.2m) contract to design, fabricate and manufacture the export pipeline, a 40t manifold and three flexible tie-in jumpers. It was also responsible for pre-commissioning, tie-ins and testing of the equipment.

HB Rentals won a $3.25m contract to supply 12 accommodation cabins for the Babbage platform. Pon Power Oil & Gas supplied the main generation system for the platform. Specialised Management Services designed the wellhead control panel / hydraulic power unit of the platform.

SGC Metering supplied a metering computer system for the field. Penspen was responsible for the detailed design of the field development and also the preliminary design of the export pipeline.