News, views and contacts from the global Offshore industry
 

Marlim Oil Field, Brazil




Key Data


Marlim is located in the north-eastern part of Campos Basin, about 110km offshore Rio de Janeiro, in water depths ranging from 650m to 1,050m. It has some 102 production wells and 50 injection wells. Over 80km of rigid pipelines and 400km of flexible lines have been laid on the field.

The field produces around 390,000 bopd and 252,000 bpd of water, and around 705,000 bwpd are injected into the field. The refinery has reported an average production of 353,027 bpd for 2007.

Discovery

Marlim was discovered by well 1-RJS-219-A in February 1985. The 75m column was predominantly unconsolidated sandstone, with a permeability as high as two darcies. The discovery also showed high-gravity oil (17-21 degree API). At the time of discovery, the Marlim reservoir had an oil-in-place volume of about 9 billion barrels and an expected 1.7 billion barrels of oil in total reserves.

Pilot well

By 1990, the field area ranged between 650m and 1,050m, and covered 137km². A pilot system was used, consisting of a semi-submersible unit with ten subsea production wells, for exporting through two monobouys to the shuttle tankers.

First development phase

The first phase was divided into two modules: module 1 was developed using the new-built semi-submersible P-18 and a former Petrobras VLCC Cairu, which was converted into P-32; module 2 comprised 12 subsea production wells and seven subsea injection wells, and was developed using the converted semi-submersible P-19.

Second development phase

The second phase, which started in June 1995, developed the southern and central areas (modules 3, 4 and 5).

Module 3

The module 3 development was based on 15 subsea production wells and ten injection wells, delivering at a rate of 100,000 bopd and 3 million square metres of gas per day, tied back to the converted semi-submersible P-26. Oil was then transferred to the existing FPSO P-33, installed as part of module 2.

"The P35 has a capacity to produce 100,000 bopd."

Built in Russia in 1984 under the name Illiad, the rig was transformed into the P26 floating production system at the Astileros shipyard in Cadiz, Spain. Conversion works took nearly two years. Expansion and reinforcement of the original structures consumed over 5,000t of steel and over 300,000m of electric cable.

Module 4

The module 4 development is based on the ore-oil VLCC José Bonifácio, which was converted into the P-35 FPSO, by Hyundai Heavy Industries, in Korea. With a length of 337m, the P35 has a capacity to produce 100,000 bopd and 3 million square metres of gas per day from 27 wells (19 subsea production wells and eight injection wells) located in two subsea manifolds, at water depths of 7,870m and 820m, respectively. It also has a storage capacity for two million barrels of oil.

The P-35 came onstream in May 1999.

Module 5

Module 5 required a larger FPU to develop a new reservoir that was found below the Marlim reservoir in the adjacent area, RJS-396. Petrobras converted another vessel, Friendship, into the FPSO P-37. This has a process capability of 150,000 bopd. It will be fed by four subsea manifolds, 20 production wells and 15 subsea injection wells. P-37 was converted in Singapore and arrived in mid-1999. It came onstream in December 1999.

"By 2008 the plant had eight FPUs with 129 subsea wells."

A second P-47 FSO plant, with a storage capacity of 1.65 million barrels of oil and the capacity to manage around 150,000 barrels per day, was developed to enhance the capacity of oil treatment of the field in 2005.

The company had earlier planned that the field development would comprise 135 subsea wells and 20 water injection wells linked to nine FPUs. However, by 2008 the plant had eight FPUs with 129 subsea wells including 86 production and 43 water injections, five subsea manifolds and two FPSOs. The field development was completed in 2002.

Contract

FMC Technologies secured a $90m contract to provide a subsea separation system for the project field in August 2009. The subsea separation module will segregate heavy oil, gas, sand, and water at water depth of around 2,950ft. The deliveries are expected to start in 2011.

Investment

The field represents a total investment of $5bn, over 15 years.

The P-19 platform, operating in the Marlim field.
The final development stage of the Marlim field will include seven foating production platforms and one floating storage unit.
Petrobras 35 is capable of processing 100,000 bopd.
Production started on 13 August 1998, when the capacity was 5,000bbls of oil/day and 50,000m³ of gas/day (1.8MMcfd), without gas lift.