Unknown will operate the upcoming El Supremo Somni de Bolivar cracking refinery, proposed to be built at Leon, Nicaragua. According to GlobalData, who tracks and profiles more than 1,400 refineries worldwide, the integrated cracking refinery will be owned by others, with operations expected to start in 2029. Buy the profile here.
Key refinery processes
Crude Distillation Unit (mbd): 150
Vacuum Distillation (mbd): 72
Catalytic Cracker (mbd): 38
Hydrocracker (mbd): 36
Reformer (mbd): 29
Hydrotreater (mbd): 95
Alkylation (mbd): 5
Isomerization (mbd): 9
During the period 2021-2025, the El Supremo Somni de Bolivar refinery cracking is expected to witness an estimated $699m of capex.
For more details on the El Supremo Somni de Bolivar cracking refinery, buy the profile here.