Girassol Luanda, Angola

Email-Icon
 
Print-Icon
 
Link-to-us
 
Related Projects
key facts
Key Data
Location
About 210km north-northwest of Luanda, Angola
Block
17
Water Depth
1,350m
Development Cost
$2.8bn
Recoverable Reserves
700 million barrels of oil
First oil
December 2001
Production
FPSO

Girassol is located about 210km NNW of Luanda, Angola. It lies in 1350m of water and has been developed using a subsea facility tied back to an FPSO.

Girassol base-case reserves are around 700 millions of barrels (bbls) of 32° API crude. The field came on-stream in December 2001.

TotalFinaElf E&P Angola is the operator of the $2.8bn project, with a 40% interest. Its partners are Esso Exploration Angola (20% interest), BP (16.7%), Statoil (13.3%) and Norsk Hydro (10%).

Subsea

The subsea production system consists of 39 wells, including 23 producers.

FPSO - Hull

The bare hull was built in Hyundai Heavy Industries (HHI) shipyard in Korea and moved out of dry dock in July 1999. It can store two million barrels of crude oil and support processes with a capacity of 200,000b/d. It has an overall length of 300m, a moulded breadth of 59.5m, a moulded depth of 30.5m and a design draught of 22.77m. The design life of the hull is 20 years without dry docking.

Deadweight is 343,000t which includes 98% of cargo capacity and 50% of slop tanks.

The hull features a double-sided construction with 12 ballast wing tanks measuring 7m wide, as well as two fore-peak and two aft-peak ballast tanks. In total, it has 12 cargo tanks.

Topsides

The main contractor, MAR Profundo Girassol - a joint venture between ETPM and Buoygues - originally subcontracted to build the integrated deck at Fos-sur-Mer in France. It subsequently re-awarded the contract to Hyundai. This deck is 180m long by 60m wide. It weighs approximately 20,000t.

It contains living quarters, oil treatment, storage, metering and offloading, gas treatment and reinjection facilities.

The process deck is located 7m above the deck of the hull. It contains facilities for produced water treatment at a flow rate of 180,000BPD as well as facilities for 3 million m³/day gas lift, 8 million m³/d gas compression at 285 bars, and gas dehydration.

Accommodation

The living quarters unit is located at the aft end of the hull and is designed to accommodate 140 people in 80 cabins.

Mooring

The FPSO was towed from Korea to Girassol, where the risers and umbilicals were installed and connected ready for commissioning and first oil.

The FPSO is spread-moored with 16 lines, four at each corner. The anchor lines are a composite assembly of chains and cables connected to 16 suction anchors.

Risers and umbilicals

The east side of the FPSO has been designed to receive the umbilicals and risers from three riser towers. Each of the riser towers is connected to the FPSO by a riser, each of which is 1.5m in diameter and 1,250m long, said to be proportionately equivalent to a 1m length of piano wire. Floats 40m high and 8m in diameter are attached to the tops of the risers, along with flexible pipelines that carry the oil up into the FPSO. Each riser tower consists of 12 tubes arranged around a thick central pipe that acts as a backbone, and the whole assembly is sheathed in epoxy insulating material.

The riser towers were built by UK-based engineering company Acergy in Sonamet, Angola.

In addition, ten umbilicals are connected to the base of the riser towers. The west side of the FPSO is designed to receive further risers and umbilicals if needed.

Offloading

The FPSO is designed for two offloading systems, one for normal operation with a buoy, one as back-up offloading, in tandem.

Both systems are located at the bow of the FPSO.

The main offloading system includes a loading buoy, located approximately one mile away from the bow of the FPSO. This can accommodate tankers from 80,000 to 400,000DWT, with a nominal offloading rate of 6,000m³/h through two rigid steel catenary 16in lines.

The tandem offloading is a conventional system with a mooring hawser assembly and handling system, and an offloading hose and its handling system. It is designed to accommodate tankers up to 200,000DWT at a nominal offloading rate of 8000m³/hour.

The field came on-stream in 2001.

Forecast production from Girassol for December 2008 was put at about 245,000 bpd.



Expand Image Expand Image
The Girassol offloading.



Expand Image Expand Image
The Girassol FPSO.



Post to:
Delicious  
Digg  
reddit  
Facebook  
StumbleUpon  

Suppliers
Acute Technological ServicesBelmet MarineCathie AssociatesChampion Environmental TechnologiesExpro Connectors & Measurements - Matre ProductsFisher OffshoreG.A. Valves SalesGeveke PompenIMECAJorinKarmsund Maritime Offshore SupplyKongsberg MarineM3 MarineMEDCORGARamnäs BrukRockbestos-Surprenant Cable CorpRoxar Flow MeasurementRoxtec MultidiameterSandvik PowdermetSemco MaritimeTwin FilterVoith TurboWilhelmsen Marine Engineering

Newsletter Sign-Up
For all the latest news in the offshore oil and gas industry, sign up here

Home
New On This Site
Products & Services
Company A-Z
Industry Projects
Special Features
Videos
White Papers
Industry News
Gallery
Events & Exhibitions
Newsletter Sign-Up
Advertise With Us
About Us
Client Area


RSS What is RSS
The website for the offshore oil and gas industry