Kali Berau Dalam is a conventional gas development located onshore Indonesia and is operated by Talisman Sakakemang. According to GlobalData, who tracks more than 34,000 active and developing oil and gas fields worldwide, Kali Berau Dalam was discovered in 2019, lies in block Sakakemang. Buy the profile here.

The project is currently in approval stage and is expected to start commercial production in 2023. The development cost is expected to be $282 m.

Field participation details

The field is owned by Mitsui, Petroliam Nasional and Repsol.

Production from Kali Berau Dalam

Production from the Kali Berau Dalam conventional gas development project is expected to begin in 2023 and is forecast to peak in 2025, to approximately 34 bpd of crude oil and condensate and 85 Mmcfd of natural gas. Based on economic assumptions, the production will continue until the field reaches its economic limit in 2038.

Remaining recoverable reserves

The field is expected to recover 47.43 Mmboe, comprised of 0.06 Mmbbl of crude oil & condensate and 284.22 bcf of natural gas reserves.

For more details on the Kali Berau Dalam Conventional Gas Field, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Oil & Gas Intelligence Center, which provides detailed profiles of 34,000+ oil and gas fields, 400,000+ exploration blocks, 1,100+ LNG terminals, 3,400+ gas processing plants, 5,000+ storage terminals, and 8,000+ pipelines, 1,400+ refineries and 13,000+ petrochemical plants worldwide.