Eni has obtained approval from Indonesian authorities for the plan of development (POD) concerning the Geliga gas field within the Ganal production sharing contract (PSC) in the Kutei Basin.
The approval came after six months after the Geliga field’s discovery and marks a key step towards exploiting an estimated eight trillion cubic feet (tcf) of gas in place from both the Geliga and Gula fields.
Discover B2B Marketing That Performs
Combine business intelligence and editorial excellence to reach engaged professionals across 36 leading media platforms.
According to Eni, the approved plan provides for the development of 5.9tcf of gas in place and 250 million barrels (mbbl) of associated condensate from Geliga, together with 2.2tcf of gas in place from the Gula field.
The Geliga field is operated by Searah, a 50-50 joint venture (JV) established by Eni and Petronas in June 2026.
Searah manages 19 assets across Indonesia and Malaysia and currently produces approximately 350,000 barrels of oil equivalent per day (boepd), with a target of surpassing 500,000boepd by 2028.
Eni anticipates that the Geliga and Gula sites will reach peak output of one billion cubic feet per day (bcf/d) of gas and 50,000bbl of condensate per day.
Development of both fields will establish a third production hub in the Kutei Basin, joining Eni’s currently operating South Hub and the North Hub, which is under construction following a final investment decision (FID) made earlier this year.
Eni expects that with these three hubs, gross production in East Kalimantan could reach about 3bcf/d of gas and 140,000bbl of condensate daily by the end of the decade.
Output from the fields will be directed to both domestic and export markets, utilising facilities such as the Bontang liquefied natural gas (LNG) plant and the Jangkrik floating production unit (FPU).
The Geliga project will include drilling 15 subsea wells and installing associated flowlines. It will also feature a newly constructed floating production, storage and offloading (FPSO) unit designed to process roughly 1bcf/d of gas and 80,000bbl of condensate per day, with a storage capacity of 1.4mbbl.
Gas processed on the FPSO will be sent by pipeline to onshore facilities at the Santan Terminal and into the East Kalimantan gas network.
Some of the gas is set to be liquefied at the Bontang LNG plant, with the rest distributed to the domestic market via pipelines. Condensate will be stabilised and kept on the FPSO, then transferred to shuttle tankers for transport.
Eni stated that the latest project will benefit from integration with the North Hub, scheduled for start-up in 2028, which is expected to streamline costs and timelines.